TBEC News
Asia Biogas and TBEC in merger to create regional champion 26 October 2016
Singapore Asia Biogas Singapore Pte Ltd (Asia Biogas) is pleased to announce that it has taken control of Thai Biogas Energy Company Limited (TBEC) and, after completion, will establish the regions largest biogas group with 12 operating projects in three countries. The merger has been approved by the shareholders of both companies and Asia Biogas has taken over management of TBEC with immediate effect. The deal is expected to close before the end of the year.
Leading Biogas Company Delivers Again: Stinking Waste Becomes Clean Energy, Act9
The TBEC TCP2 Biogas Project started commercial operations on 14, August, 2015. The 4.2 MWe project is TBEC?s second large-scale biogas plant adjacent to Tha Chang Group in Surat Thani, Thailand. The project is implemented by TBEC under a Build, Own, Operate, Transfer (BOOT) structure. In accordance with the BOOT terms, TBEC is responsible for the design, engineering, finance, construction and operation of the Biogas Power Plant. TBEC shares the revenues of the project with Tha Chang Group. The combined capacity of TBEC two biogas projects at the same location is 7 MW. In addition to producing electricity, the projects efficiently treats the wastewater, significantly reduces air emissions and eliminates the smell of open ponds to the benefit of local communities. The completion of this project raises TBEC annual emissions reductions to 400 000 per year, which is equivalent to taking 135 000 cars from the road.
TBEC CWP Biogas Project was first synchronized
TBEC CWP Biogas Project was first synchronized to the grid on 24th February, 2015. The project is the first large-scale biogas plant in Phang-Nga with a capacity of 2.8 MWe. It is also the 8th biogas project by TBEC and was completed in 10 months with a budget of THB 190 million. The TBEC CWP Biogas Project is the first of a series of 5 projects with a joint capacity of 20 MWe and investment cost of THB 1.1 billion (USD34 million) that TBEC is commissioning in 2015-2016 in South Thailand, an area that has suffered electricity blackouts due to demand clearly outstripping supply.
TBECs turnkey projects won the Thailand Energy Awards 2014 in Off Grid category
Bangkok TBECs turnkey projects, Thai Wah and Thai Nam biogas projects won the awards for Best Off-Grid Biogas Project at the Thailand Energy Awards 2014. General Prayuth Chan O Cha, Thailands?s prime minister, handed out the awards on November 21st, 2014 at the Government House. The ceremony was organized by Department of Alternative Energy Development and Efficiency, Ministry of Energy.
NCPO observes electricity security in South
NAKHON SI THAMMARAT, June 16 -- National Council for Peace and Order Deputy Chief PrachinChantong travelled to southern region to observe power plants operation and ensure energy security in the region.
ICBC (Thai), GuarantCo collaborate on Bt402m loan to Thai Biogas Energy
GuarantCo and Industrial and Commercial Bank of China (Thai) have jointly created an innovative financing structure, providing a loan of Bt402 million to Thai Biogas Energy Co (TBEC) for construction of two new biogas projects.
BIO signed a credit facility agreement worth EUR 1,37 million
BIO signed a credit facility agreement worth EUR 1,37 million with Thai Biogas Energy Co Ltd (TBEC), to finance the first ever biogas installation in Lao
TBEC won the awards from Thailand Energy Awards 2010 -On Grid category
In this auspicious occasion, we are honored by His Excellency Mr. Abhisit Vejjajiva, Prime Minster of Thailand, presided over the Thailand Energy Awards 2010 on 30 August 2010 at Santi Maitri Build, Government House.
 
BIO-TBEC SIGN AGREEMENT WORTH EUR 1.37 MILLION INVESTMENT IN LAOS.
BIO join ranks of DFIs that support TBEC.
Discussion Query: The project is the Clean Development Mechanism projects (CDM-PoA)
Thai Biogas Energy Company Limited (TBEC) cordially invites you to STAKEHOLDER CONSULTATION: TBEC Biogas Programme of Activities PoA
to discuss TBECs plans for the CDM PoA which will include a summary of the project design and discussion of environmental and social impacts
TBEC - Winner of ASEAN Renewable Energy Awards - On Grid category
The Awarding Ceremonies was held on 22 July 2010 at Dalat, Vietnam.
INITIAL STAKEHOLDER CONSULTATION: TBEC LIG PROJECT
Wat Naxone, 13 South Road, Km 47, Ban Naxone, Pak Ngum District, Vientiane Capital, Lao PDR 16th March 2010
INITIAL STAKEHOLDER CONSULTATION: TBEC LIG PROJECT
Wat Naxone, 13 South Road, Km 47, Ban Naxone, Pak Ngum District, Vientiane Capital, Lao PDR 16th March 2010 between 09.00 a.m. 01.30 p.m.
TBEC has earned the Crown Standard in the Crown Standard, CDM Press release
by Thailand Greenhouse Gas Management Organization (Public Organization) on Thursday 1st December 2009, at Rama Garden Hotel Bangkok.
BOOT Contract Signing Ceremony between Lao-Indochina Group Co., Ltd. (LIG) and Thai Biogas Energy Co., Ltd.
on Friday 20th November 2009 , at Lao Plaza Hotel, Vientiane, Lao PDR. (Newspapers / Photo))
TBEC on the Nation "Green Energy policy to benefit biogas producer"
by Mr. Pajon Sriboonruang On May 18, 2009.
On Air Interview: Biogas Technology and TBEC Tha Chang Plant
by Mr. Pajon Sirboonruang

On Air Interview: Biogas Technology and TBEC Tha Chang Plant
by Mr. Pajon Sirboonruang on Thursday, March 19, 2009, F.M. 101 MHz, Surat Thani
Grand Opening Ceremony of TBEC Tha Chang plant
Grand Opening Ceremony of TBEC Tha Chang plant on Friday, March 23, 2009 at Surat Thani.
2nd Stakeholder Consultation, Tha Chang Palm Oil Project
29th January, 2009 at the Tha Chang Subdistrict Administrative Organization, Tha Chang, Surat Thani
by The Thai Biogas Energy Company, TBEC
brother